📈 15.0 Optimize planning
Summary
- Milestone dates: 2022-04-18 to 2022-05-17
- Build board
Removals and Deprecations ❗ ❗
Capacity / OOO
- 1.5 BE
- 1 FE
- 0.5 UX
Planned OOO (Please order by From date):
| Person | From | To | Days |
|---|---|---|---|
| Haim | 18 | 21 | 4 |
| Pavel | 18 | 26 | 6 |
| Ezekiel | 25/04 | - | 1 |
Objectives (WIP)
- Completion of the DORA 4 Metrics APIs
🏆 - VSA backend date range rebuild
- VSA usability improvements
😍 🏆
Themes
-
🏎 Performance -
🔒 Security -
😍 Usability -
📈 Customer Requests -
🏆 OKR -
🐛 Bug
GitLab Product Themes
Optimize FY23-Q1 Shared OKR
OKRs
- Optimize: Burn down 30% of SUS issues
- Optimize: Close 10 Dev security burndown issues
- Optimize: Finish the VSA date selection correction
- Optimize: Resolve 3 blocked tests
- Optimize: Complete VSA - Highlight outlier stages issues
To-Do
-
Define an approximate scope for the coming release. - Apply appropriate labels to issues:
-
Priority -
Department -
Pricing Tier
-
-
Review the proposed scope with Engineering. -
Review design objectives with UX. -
Get feedback and estimates from Engineering, confirming scope for the release. -
Final verification of issues scheduled for the release. -
Present selected issues in the Manage Kickoff on the 17th!
Previous 14.10 <= => 15.1
Edited by Haim Snir