FY21-Q4 Ops Sub-Department OKRs
ARR Objective - Raise bar on quality and reliability
-
10% of Ops Sub-dept engineers have commits to e2e tests
- Continuous Delivery: #9691 (closed)
- Verify: #9539 (closed)
-
50% of Ops Sub-dept teams have a documented quality process
- Continuous Delivery: #9690 (closed)
-
50%+ of Incident Reviews involving Ops team include meaningful participation from an Ops team member
- Continuous Delivery: #9692 (closed)
Product Objective
-
Improve Large Contentful Paint (LCP) performance for high priority endpoint in each stage.
- Continuous Delivery: #9685 (closed)
- Verify: #9541 (closed)
-
Increase Narrow MR Rate from 9 to 10
- Continuous Delivery: #9683 (closed)
- Verify: #9542 (closed)
- Run demo process, significant feature progress each release, and <5 min production app capability no later than Jan 22
Team Objective
- Key Result: Support Infrastructure Stable Counterparts
- Performance reviews completed by Jan 31, 2021 =>
100%; Completed
Edited by Sam Goldstein