Lorie Whitaker Transition Issue
Overview
This issue will serve as a tracker for the transition for Lorie Whitaker out of the role of Staff UXR with Verify, Package, and Release.
Transition Overview
- Announcement Date: 2021-03-22
- Effective Date: 2021-04-02
Opening Tasks
-
Create transition issue -
Share issue with Manger -
Share relevant documents with parties
Current Research Projects:
| Issue | DRI | Remaining Tasks |
|---|---|---|
| 1161 | @jreporter | More participants are needed. Dovetail project |
| 10466 | @jreporter @asmolinski2 | Discussion guide, recruiting issue, and screener created. All that remains is research to be conducted and analysis of findings. |
Other Current Projects:
| Issue | DRI | Remaining Tasks |
|---|---|---|
| 10749 | @asmolinski2 | Wrap up conversations with team members around changes to duties to address the engagement survey issues |
| 11088 | @fseifoddini | Farnoosh has sent the survey out. We will meet to analyze the data on March 29 |
| 1244 | @jheimbuck_gl | James will continue with this effort |
| 1249 | @ogolowinski | Orit needs to recruit and conduct research for this. I've helped with discussion guide and screener. |
Timeline
Week 1 - March 22-26, 2021
-
Share issue in your impacted channels -
Schedule syncs with Transition Parties (as needed) -
Transition any open research issues
Week 2 - March 29 & 30
-
Schedule syncs with Transition Parties (as needed)
Closing Tasks
-
Mark all tasks as complete -
Close Issue
Edited by Lorie Whitaker