docs(roadmap): rename closed-beta to beta, add the Transcend goal and a GA horizon
What
Open beta is announced 2026-10-06 at GitLab Transcend, which makes it the beta phase's governing date. The roadmap document covered only the closed stage, so it is renamed to cover beta as a whole, and the new dates are recorded.
Four changes, in the order asked for:
| Ask | Where |
|---|---|
| Rename closed-beta → Beta, leave a reference | docs/roadmap/closed-beta.md → docs/roadmap/beta.md, with the rename recorded in that file's header |
Point roadmap.md at beta |
docs/roadmap.md names the three stages and points at beta.md; it carries no dates |
| Add the Transcend goal | Header note, ## Delivery timeline (forecast), the milestone table, and the Gantt |
| Add a GA target | Milestone table and a new ## After Transcend, and the road to GA, carrying spine.md's January 2027 |
The rename, and the thing that nearly went wrong
143 references in this repo match closed-beta.md. Only 15 of them are the roadmap. The other
128 point at docs/specs/S20-a-lifecycle-closed-beta.md (110) and
docs/plans/2026-08-11-s20a-lifecycle-closed-beta.md (12) — filenames that carry "closed beta" as
an S20-A scope phase, not as the roadmap. A path-wide rename would have broken every one of
them.
This MR updates every link that resolves to roadmap/closed-beta.md and leaves all 122 S20-A references
untouched; the counts are asserted before and after in the commit. git records the move as a
rename at 94% similarity, so the diff reads as a move plus content edits rather than a delete and
an add.
The old path is removed, not stubbed. "Leave a reference" is satisfied by a note in the
document and in the index; a stub file at the old path would be a permanently stale second copy.
The cost is that absolute GitLab URLs to docs/roadmap/closed-beta.md in already-closed sprint
issues will 404 — worth naming, and judged cheaper than the stub.
Three names deliberately did not change, and both documents say so, because a reader who assumes they did will query for things that do not exist:
- the launch-gate label is still
~AR-Blocks::Closed-Beta - the group milestone is still
CD: Closed Beta unified-artifact-management's scope document is stillclosed-beta-scope.md
Two are GitLab objects and one is another project's file. Renaming them is not this document's to do, so every reference below uses the real names.
Dates
2026-10-06 Open Beta is the current target, in the milestone table and the Gantt (mOB).
It is an announcement, not a second gate — the only launch gate defined anywhere is still the
open ~AR-Blocks::Closed-Beta list being empty, which stands at 1. The document declines to
invent an open-beta entry criterion and says where one belongs (closed-beta-scope.md, with
Product) if one is needed, flagging that its absence is better settled before 10-06 than at it.
2026-10-02 is superseded, not deleted — eight days before it fell due, having been set only the day before. The date history is now a table that distinguishes the two ways a date leaves, because they read identically in a list and mean different things about delivery:
| Date | How it ended |
|---|---|
| 2026-09-07 | Passed unmet |
| 2026-09-11 | Passed unmet |
| 2026-09-15 | Passed with the gate open; spine.md now records it as the .com Closed Beta date |
| 2026-10-02 | Superseded while still in the future |
| 2026-10-06 | Current |
The stages and dates follow spine.md. unified-artifact-management!151 (merged
2026-09-23) records .com Closed Beta on 2026-09-15, exiting at Gate 1 (~2026-10-08), .com Public
Beta on 2026-10-06, and GA for every deployment in January 2027 (19.8). beta.md's header carries
that as a stage table. The two beta stages overlap, and the document reports the label gate rather
than a closed-beta start date.
GA is spine.md's January 2027. It is Product's date and has had no engineering planning pass.
Sync Step 10 now reads "do not add or change GA dates without explicit user instruction", and the
GA row records that it was added on that basis.
## After Transcend, and the road to GA
New section covering the regroup fortnight — engineering GA scope defined from Product's once
final, a retro, AI best practices — and why roadmap/ga.md stays unwritten until the scope
document lands (an empty GA roadmap is honest; a speculative one gets read as scope).
It carries one finding forward so the GA scope pass does not rediscover it: the fast-follow list is not homogeneous. Unfinished feature work will be delivered or cut, but S15 step 16 and #278 are externally gated on the registry-conformance rc#33 handoff, which no AR sprint can clear. GA scope that folds them in with deliverable work inherits a dependency it cannot schedule.
One judgment call to flag
### Deferred from closed beta is retitled ### Deferred from beta, with a sentence stating that
both deferrals were taken against closed beta and that the open-beta announcement does not
reinstate them. That is a consistency edit, not a new scope decision — and the note says
reinstating either is a product decision in closed-beta-scope.md, not a roadmap edit. No inbound
link uses an anchor in this file (verified), so no heading change breaks a reference.
Verification
vale,markdownlint-cli2,trailing-whitespace,end-of-file-fixer,editorconfigall pass on every changed file.- All 15 sections present; no table has inconsistent column counts; all three ```mermaid fences balanced.
- Every relative link in
beta.mdresolves (0 broken), and a repo-wide link check finds no new breakage — the 16 pre-existing hits are template placeholders (SXX-name.md,{page}.md) and worktree copies, none of them the roadmap. - Reference counts asserted:
roadmap/closed-beta.md→ every link updated except one comment in an immutable migration (20260831103000_add_id_uuid_version_checks.sql:80, whichlint:migration-immutabilityprotects); S20-A spec → 110 preserved; S20-A plan → 12 preserved.
Note on docs/roadmap.md
beta.md's own sync workflow lists docs/roadmap.md on its Step 10 do-not-touch list. This MR
edits it under explicit instruction, because the rename changes the path the index points at. The
file stays an index: the stage names and links only, with every date in beta.md.
Related to #1416 (closed)