📈 14.9 Optimize planning
Summary
- Milestone dates: 2022-02-18 to 2022-03-17
- Build board
Capacity
Please order by From date:
| Person | From | To | Total working days |
|---|---|---|---|
| @m_frankiewicz | 2022-03-04 | 2022-03-15 | 7 |
Objectives (WIP)
- Continue work on Dev section security burndown
- VSA backend date range rebuild
- VSA usability improvements that don't require BE support
- Feature work on our high usage areas
- Contribute to a larger frontend effort
Themes
-
🏎 Performance -
🔒 Security -
😍 Usability -
📈 Customer Requests -
🏆 OKR -
🐛 Bug
| Title | Link | Weight | Theme | Priority |
|---|---|---|---|---|
| Deprecate segmented control > /vue_shared/components/ci_cd_analytics/ci_cd_analytics_charts.vue | gitlab-org/gitlab#348103 (closed) | 2 | ||
| Follow-up: FOSS VSA specs should reflect component directory structure | gitlab-org/gitlab#338547 (closed) | 1 | ||
| Follow-up from "VSA - Create value stream form UX improvements" | gitlab-org/gitlab#323889 (closed) | 1 | ||
| GlTable: Add tooltips to provide more information about table sorting | gitlab-org/gitlab-ui#1447 (closed) | 3 | ||
| [VSA] UX for aggregated data | gitlab-org/gitlab#341739 (closed) | umbrella issue |
|
priority1 |
| [VSA] Add empty state at the group level when there are no custom value streams | gitlab-org/gitlab#351853 (closed) |
|
priority1 | |
| [VSA] Allows user to switch between new and old backend | gitlab-org/gitlab#352428 (closed) |
|
priority1 | |
Replace data-confirm modals with GlModal in app/views/admin/applications/_delete_form.html.haml
|
gitlab-org/gitlab#344207 (closed) | 2 | ||
Replace data-confirm modals with GlModal in app/views/admin/topics/_form.html.haml
|
gitlab-org/gitlab#344184 (closed) | 2 | ||
Migrate app/views/admin/users/_modals.html.haml modal implementation to GlModal
|
gitlab-org/gitlab#344555 (closed) | 3 | ||
| API support for Time to restore service | 3 | medium |
Research/Needs Weight 🕵 ️
- TBD
To-Do
-
Define an approximate scope for the coming release. -
Apply appropriate labels to issues: -
Priority -
Department -
Pricing Tier
-
-
Review the proposed scope with Engineering. -
Review design objectives with UX. -
Get feedback and estimates from Engineering, confirming scope for the release. -
Final verification of issues scheduled for the release. -
Present selected issues in the Manage Kickoff on the 17th!
Previous 14.8 <= => Next 14.10
Edited by Haim Snir