DAC - Rollup node integration
Owner: @andrea.cerone
This milestone tracks all the remaining work that needs to be done on the rollup node to integrate with DAC.
Main milestone for DAC production readiness is %Data Availability Committee (DAC) II - Production readiness The milestone can be considered completed when all the following tasks have been completed:
-
Rollup node is able to run components asynchronously -
Rollup node stops the interpreter if reveal data is not available -
Rollup node requests missing data to sidecar -
Rollup node restarts interpreter once missing data is found