馃摝 14.7 Planning for Import
Team
~11353826
- 2 BE
- 1 FE
- 1 SET
- 1 shared SEC
- 0.5 UX (TBH)
Capacity / OOO
- Team members - Planned OOO
- Haris: 20 Dec - 03 Jan
- Andrey: Not OOO, but I will be shifting my working hours closer to US Eastern time zone starting from January
- George - Dec 21 - 28
- Kassio - Dec 23 - 03 Jan
- 30% of SET team capacity is dedicated to
Team Velocity
(from: https://app.periscopedata.com/app/gitlab/698723/Manage::Import-Backend-Overview snapshot date: 14 Dec 2021)
Proposed Objectives
-
backend Continue with Headcount Reset priorities
- Project Migration MVC
- Security
- Bugs / Reliability / Performance issues
-
frontend
- Ensure proper validation for GIT url is performed for all requests - follow-up from previous git validation work, not all cases were handled
-
View History of All Project Imports
- This was identified as a good starting point at gitlab-org/gitlab#343616 (comment 743740108)
- will be split in two separate issues:
-
backend, weight
5锔忊儯 - increased weight since it will be implemented by @xanf as frontend person (gitlab-org/gitlab#331567 (closed)) -
frontend, weight
3锔忊儯 (gitlab-org/gitlab#267788 (closed))
-
backend, weight
- Quality
Boards
Out of scope
Following issues were recently discussed, but are not in scope for %14.7:
- TBD
TODO
-
Schedule the planning call. 15 Dec @ 9:30 EDT; 15:30 CET
-
Write milestone objectives. -
Review the roadmap with the team. -
Review milestone objectives with the team. -
Discuss capacity (OOO plans, Headcount Reset). -
Team planning to highlight/guess issues that can be delivered in 14.7, label Deliverable and set milestone to 14.7
. -
Publish the planning call video: Unfiltered -
Clone the planning issue for the next milestone and link to this one.