14.7 Optimize planning issue

%14.7 Milestone Planning for groupoptimize


Capacity

  • Family & Friends Day 2021-12-27
  • Family & Friends Day 2022-01-03

Please order by From date:

Person From To Notes
@ahegyi TBD TBD ~7 days (~50% capacity for the milestone)
@blabuschagne  20 Dec  4 Jan  ~50% capacity for the milestone
@wortschi 23 Dec  28 Dec  5 days
@ekigbo 24 Dec 5 Jan Plus 1/2 day 23rd Dec
@npost 13 Dec 4 Jan ~7 days
@mfrankiewicz 24 Dec ~5 Jan plus 13 Dec and half day Dec 21

Objectives

  1. Continue work on Dev section security burndown
  2. VSA backend date range rebuild
  3. VSA usability improvements that don't require BE support
  4. Feature work on our high usage areas
  5. Contribute to a larger frontend effort

Themes

  • 🏎 Performance
  • 🔒 Security
  • 😍 Usability
  • 📈 Customer Requests
  • 🏆 OKR
  • 🐛 Bug
Title Link Weight Theme Priority
[VSA] Display project for each record in group level feature gitlab-org/gitlab#215290 (closed) 3 😍
Simplify analytics borders, padding and margins gitlab-org/gitlab#217485 (closed) 1
Tabs > HAML > Migrate ee/app/views/groups/epics/show.html.haml to GlTabs gitlab-org/gitlab#230790 (closed) 2 🏆
Migrate app/views/shared/_confirm_fork_modal.html.haml modal implementation to GlModal gitlab-org/gitlab#344566 (closed) 3 🏆

Research/Needs Weight 🕵🏻‍♂️

To-Do

  • Define an approximate scope for the coming release.
  • Apply appropriate labels to issues:
    • Priority
    • Department
    • Pricing Tier
  • Review the proposed scope with Engineering.
  • Review design objectives with UX.
  • Get feedback and estimates from Engineering, confirming scope for the release.
  • Final verification of issues scheduled for the release.
  • Present selected issues in the Manage Kickoff on the 17th!

Previous <= => Next

Edited by Martin Wortschack