[VSA] Change Total time chart (previously "days to completion") to lead time and cycle time
Problem
- "Days to completion for all stages" is a roundabout way of saying "lead time".
- The current scatterplot is not an appropriate chart for something with so much content
- It would be nice to see cycle time and lead time superimposed
Proposal
-
Replace scatterplot for a line chart in the overview sectionthis will be part of #346554 (closed) - Use cycle time and lead time
- Add tooltips with the definition of cycle time and lead time
- Align on definitions of lead time and cycle time
TODO
-
backend VSA Endpoints for lead/cycle time as time serie... (#361746 - closed) -
frontend Rename the chart to "Lead time and Cycle time" -
frontend Update the chart to use the values from the new lead / cycle time endpoint(s) - Add tooltips with the definition of cycle time and lead time ??