Pipeline paused => cancelled => retried causes weird pipeline/build statuses
Hi there!
I am a GitLab.com user with private repositories. I was waiting for a pipeline to finish but eventually killed it by clicking on "cancel" button.
I then retried it, but it looks like all stages have been restarted at the same time, not respecting the scheduling and preconditions between the stages:
A couple of things related to this pipeline:
- Normally, the "archives" build should not be triggered before the "integration" and "maven" builds;
- If one of them fails, it is expected to abort the whole pipeline;
- The "experimental" deploy job is triggered manually, and I did not trigger it for this pipeline (I swear it);
Regards.