14.7 Purchase Planning Issue
14.7 Milestone Information
- Start date: 2021-12-18
- End date: 2022-01-17
-
Issue board
- Issues within each list are prioritized with the highest priority issues ranked from top to bottom, please pick issues in order wherever possible
- Issues marked with Deliverable are issues we are committing to deliver in the current milestone
- 14.7 Fulfillment retrospective: coming soon
Milestone Summary
🏋 Planned capacity
Click to see the breakdown of team capacity for the milestone
Formula: 1 engineer = 10 weight / milestone (21 work days) = 0.48 weight per day
Team | Engineer | # Working Days => # Weight (rounded up) |
---|---|---|
FE | Diana | 12 => 6 |
FE | Angelo | 4 => 2 |
FE | Vamsi (onboarding) | 8 => 4 * 0.5 (due to onboarding) => 2 |
frontend | TOTAL | 10 |
BE | Josianne | 9 => 5 |
BE | Qingyu | 10 => 5 |
BE | Shreyas | 12 => 6 |
BE | Ryan (on InfraDev) | 0 => 8 |
backend | TOTAL | 24 |
⭐ Priority Projects
Epic / Issue | Status | Teams | Target Milestone |
---|---|---|---|
[QSR] [SM & SaaS] max_seats_used is not reset after subscription renewal, causing the reconciliation quantity to be incorrect gitlab-org&7258 (closed) | workflowin dev | backend | %14.7 |
Move Storage purchase flows to GitLab.com (Group namespaces only) gitlab-org&5789 (closed) | workflowin dev | frontend | %14.7-%14.8 |
[QSR] [SaaS] Create transparency about User Overage process at the time of adding users gitlab-org&7230 The goal for this milestone is to break down the work and do refinement for these issues, so that we are ready for dev in 14.8. |
workflowplanning breakdown | backend frontend | %14.7 |
[QSR] [SaaS] Create transparency about User Overage process at the time of purchase gitlab-org&7229 (closed) |
workflowdesign | UX | %14.8 |
Strict Cloud Licensing for Self-Service Net New Purchase https://gitlab.com/groups/gitlab-org/-/epics/7263 There are 2 FE issues that we'll be helping with - the backend is being done by License team. |
workflowrefinement | frontend | %14.8 |
Move CI Minutes purchase flows to GitLab.com (Group namespaces only) gitlab-org&6574 (closed) Only the cleanup work remaining |
workflowin dev | frontend | %14.6-%14.8 |
🚀 Deliverables
We are committing to delivering these issues in the current milestone, so they should be prioritized above non-priority, non-deliverable issues.
🖼 In Design
Take a look at what Emily is working on here.
Weight by workflow label at beginning of milestone
Team | Ready for Dev | In Dev | In Review | Blocked | Production | Total |
---|---|---|---|---|---|---|
frontend | 7 | 7 | - | 1 | - | 15 |
backend | - | 22 | 7 | - | - | 29 |
Milestone Weight History
Fulfillment Milestone Weight History
Click to view milestone weight history for BE and FE
frontend | 14.2 | 14.3 | 14.4 | 14.5 | 14.6 | 14.7 |
---|---|---|---|---|---|---|
Total assigned | 26 | 17 | 20 | 25 | 17 | 15 |
Unplanned | 19 | 1 | 10 | 7 | 13 | 0 |
Pushed to next milestone | 8 | 9 | 9 | 10 | 13 | 6 |
Deliverable | - | 7 | 5 | 5 | 6 | 9 |
Closed | 41 | 9 | 24 | 22 | 15 | 9 |
backend | 14.2 | 14.3 | 14.4 | 14.5 | 14.6 | 14.7 |
---|---|---|---|---|---|---|
Total assigned | 56 | 37 | 43 | 29 | 34 | 29 |
Unplanned | 13 | 13 | 6 | 20 | 19 | 5 |
Pushed to next milestone | 5 | 29 | 22 | 8 | 24 | 9 |
Deliverable | 17 | 16 | 15 | 6 | 17 | 12 |
Closed | 44 | 21 | 27 | 41 | 26 | 17 |
Team Holiday Time
We have quite a bit of holiday time in December
Please add your holiday dates below for the 14.7 release period and don't forget to add to the Fulfillment calendar.
Family & Friends |
Public Holiday |
Vacation |
Total days | |
---|---|---|---|---|
Product Manager | ||||
Tatyana |
Dec 27 Jan 3
|
Dec 24 Dec 31
|
Dec 23 - Jan 3 |
8 |
Product Designer | ||||
Emily |
Dec 27 Jan 3
|
Dec 23-24 Dec 31
|
Dec 20 - Jan 3 |
11 |
Engineering Manager | ||||
Ragnar |
Dec 27 Jan 3
|
Dec 24 Dec 31
|
Dec 23 - Jan 3 |
8 |
Software Engineers: Frontend | ||||
Angelo | Jan 3 |
Jan 6 |
Dec 14 - Dec 31 |
17 |
Diana |
Dec 27 Jan 3
|
Jan 6 |
Dec 24 Dec 28 - Dec 29 Jan 3 - Jan 16
|
12 |
Vamsi |
Dec 29 Jan 5
|
Dec 27 - Dec 28 Jan 3 - Jan 4
|
Dec 20 - Dec 24 Dec 30 - Dec 31
|
13 |
Software Engineers: Backend | ||||
Shreyas |
Dec 27 Jan 3
|
Dec 24 |
9 | |
Qingyu |
Dec 24 Jan 4
|
Dec 27 - Dec 28 Jan 3
|
Dec 29 - Dec 31 Jan 05 - Jan 07
|
11 |
Josianne |
Dec 24 Jan 5
|
Dec 27 - Dec 28 Jan 3 - Jan 4
|
Dec 29 - Dec 31 Jan 06 - Jan 10
|
12 |
Software Engineers: unavailable | ||||
Ryan (InfraDev work) | ||||
Software Quality Engineer(s) | ||||
Chloe |
Announcements
@rhardarson is out January 10th to 24th - @agulina and @qzhaogitlab will be DRIs for any EM group specific responsibilities - Coverage issue
Purchase Roadmap
Please see this issue https://gitlab.com/gitlab-org/fulfillment-meta/-/issues/301 for Purchase Roadmap FY22-Q4