馃摝 14.7 Planning for Import

Team

~11353826

  • 2 BE
  • 1 FE
  • 1 SET
  • 1 shared SEC
  • 0.5 UX (TBH)

Capacity / OOO

  • Team members - Planned OOO
    • Haris: 20 Dec - 03 Jan
    • Andrey: Not OOO, but I will be shifting my working hours closer to US Eastern time zone starting from January
    • George - Dec 21 - 28
    • Kassio - Dec 23 - 03 Jan
  • 30% of SET team capacity is dedicated to

Team Velocity

image
image
(from: https://app.periscopedata.com/app/gitlab/698723/Manage::Import-Backend-Overview snapshot date: 14 Dec 2021)

Proposed Objectives

Boards

Out of scope

Following issues were recently discussed, but are not in scope for %14.7:

  • TBD

TODO

  • Schedule the planning call. 15 Dec @ 9:30 EDT; 15:30 CET
  • Write milestone objectives.
  • Review the roadmap with the team.
  • Review milestone objectives with the team.
  • Discuss capacity (OOO plans, Headcount Reset).
  • Team planning to highlight/guess issues that can be delivered in 14.7, label Deliverable and set milestone to 14.7.
  • Publish the planning call video: Unfiltered
  • Clone the planning issue for the next milestone and link to this one.
Edited by Illya Klymov