Pipeline Execution 15.4 Planning issue
Issue Boards
PE workflow board | Issues by Team Member
🎥
Recordings - Refinement Kickoff call - Published 2022-07-18
- Milestone Kickoff Call w/ UX
This issue is closed as of 2022-08-17
The Single Source of Truth (SSOT) for the status of issues in the milestone is the milestone board where issues are stack ranked by priority.
Theme: Improve the developer experience when troubleshooting pipelines.
Goals for the milestone
- Meet Reliability issue SLOs - VerifyP1 issues -> Contributes to GitLab Hosted First investment theme
- Address Compliance initiatives
- Improve the developer experience of troubleshooting pipelines -> Contributes to the Improve Key workflow usability Investment Theme
VerifyP1
-
https://gitlab.com/gitlab-org/gitlab/-/issues/356310+ -
Confidential Issue - https://gitlab.com/gitlab-org/gitlab/-/issues/363711 -
Confidential Issue - https://gitlab.com/gitlab-org/gitlab/-/issues/363745 -
Confidential Issue - https://gitlab.com/gitlab-org/gitlab/-/issues/364586
VerifyP2
-
Frontend: UI updates when max jobs limit is rea... (gitlab-org/gitlab#329926 - closed) -
Backend: Add `partition_id` column to selected ... (gitlab-org/gitlab#364393 - closed)
VerifyP3
-
Backend: Make it easier to understand and diffe... (gitlab-org/gitlab#217718 - closed) -
Backend: Scheduled pipelines are triggering mul... (gitlab-org/gitlab#338609 - closed) -
Backend: Job ignores previous stage if cancelle... (gitlab-org/gitlab#207988 - closed)
Other bugs/Issues
-
Frontend: Remove shared runner usage tab from g... (gitlab-org/gitlab#362518 - closed) -
Failure in browser_ui/4_verify/pipeline_status_... (gitlab-org/gitlab#363633 - closed)
Feature flag
-
issue
Quality tests
Docs improvement
-
Add issue here - link -
Add issue here - link
%15.3 carryover)
Issue Breakdown (As of 2022-08-16 - excludingIssue Type | Issues | Weight | Percentages issues/weight |
---|---|---|---|
~"type::feature" | 7 | 16 | 33.33% / 36.36% |
~"type::bug" | 7 | 15 | 33.33% / 34.09% |
~"type::maintenance" | 7 | 13 | 33.33% / 29.55% |
Designer/UX
- Epic: gitlab-org&5866
Planning Tasks
-
PM highlights work for Deliverables, User Experience, Bug Fixes, Security Fixes, Technical Debt sections -
PM describes how this milestone aligns with the company's OKRs -
EMs assign issues with ~needs weight
label in~workflow::planning breakdown
to engineers for review ahead of the milestone kickoff. -
By the 15th - EM applies ~deliverable
and~stretch
labels to issues. -
Engineers begin working on issues in workflow::ready for development
Edited by James Heimbuck