Pipeline Execution 15.3 Planning issue
Issue Boards
PE workflow board | Issues by Team Member
This issue is closed as of 2022-07-17
The Single Source of Truth (SSOT) for the status of issues in the milestone is the milestone board where issues are stack ranked by priority.
🎥
Recordings - Refinement Kickoff - Posted 2022-06-21
- Kickoff Video - Posted 2022-07-12
Theme: Improve the Pipeline experience for Open Source Program project contributors.
Goals for the milestone
-
Meet Reliability issue SLOs - VerifyP1 issues -
Open Source Program projects and their contributors should have a great experience running pipelines on GitLab
VerifyP1 (Infradev, Security, Application limit, etc.)
-
Confidential issue - gitlab-org/gitlab#359039 (closed) -
Confidential issue - gitlab-org/gitlab#243703 (closed) -
Confidential issue - https://gitlab.com/gitlab-org/gitlab/-/issues/358075 -
Confidential issue - https://gitlab.com/gitlab-org/gitlab/-/issues/363725 -
Confidential issue - https://gitlab.com/gitlab-org/gitlab/-/issues/363711 -
Confidential issue - https://gitlab.com/gitlab-org/gitlab/-/issues/356310
VerifyP2
-
Confidential issue - https://gitlab.com/gitlab-org/gitlab/-/issues/364282 -
Backend: Use a reduced cost factor for public f... (gitlab-org/gitlab#346400 - closed) -
Backend: Harden CI limit for public projects (gitlab-org/gitlab#337245 - closed) -
Backend: Use a reduced cost factor for contribu... (gitlab-org/gitlab#352830 - closed) -
May Move to next milestone - Backend: Set Public OSS plan cost factor to .5 (gitlab-org/gitlab#351933 - closed)
VerifyP3
-
Frontend: Reduce the complexity of `handleMerge... (gitlab-org/gitlab#350804 - closed) -
Frontend: Show Pipeline tab on MR if no pipelin... (gitlab-org/gitlab#329787 - closed)
Feature flag
Docs improvement
-
Add issue here - link -
Add issue here - link
Issue Breakdown Current
- Expected Issue Capacity - 40
- Expected Carryover - 17
- Target planned issues - 23
- Issue Type Split Target - 25% Features, 25% Bugs, 50% Maintenance
Issue Type | Issues Planned (target before carryover) | Weight | Percentages issues/weight of Planned |
---|---|---|---|
~"type::feature" | 5 (5) | 9 | 15% / 14% |
~"type::bug" | 7 (6) | 16 | 20% / 30% |
~"type::maintenance" | 22 (12) | 38 | 65% / 56% |
Other | 0 |
Designer/UX
- Epic: gitlab-org&5866
Planning Tasks
-
PM highlights work for Deliverables, User Experience, Bug Fixes, Security Fixes, Technical Debt sections -
PM describes how this milestone aligns with the company's OKRs -
EMs assign issues with ~needs weight
label in~workflow::planning breakdown
to engineers for review ahead of the milestone kickoff. -
By the 15th - EM applies ~deliverable
and~stretch
labels to issues. -
Engineers begin working on issues in workflow::ready for development
Edited by James Heimbuck