FY21-Q1 Plan:Project Management Support Incremental ACV => 83%
Key Results
-
Deliver four ~"planning priority" items directly tied to revenue
=> 33%
-
Deliver 5 performance or Application Limits issues
=> 100%
- gitlab-org/gitlab#34030 (closed)
- gitlab-org/gitlab#196883 (closed)
- gitlab-org/gitlab#208094 (closed) (fixed by Thong)
- gitlab-org/gitlab#32455 (closed)
- gitlab-org/gitlab#39453 (closed)
- https://gitlab.com/gitlab-org/gitlab/-/issues/55241
- Excludes ~"Community Contribution"
CC @donaldcook
Retrospection
Good
- We identified that feature progress wasn't satisfactory during the quarter and introduced measures, such as feature channels in Slack, to help.
- We made measurable progress against making our part of GitLab more reliable, performant and enjoyable to use.
- Significant progress against the feature goals we didn't complete that should see them completed in the next quarter. (See Real-Time Working Group and #f_timeboxes and #f_burnup-charts)
Bad
- Insufficient progress overall against our feature commitments.
Try
- Document the Themes process in the handbook so that it can be run from the start of the next quarter (!49342 (merged))