... | ... | @@ -34,10 +34,11 @@ Please take a look at the section below for your WG and update it as follows: |
|
|
|
|
|
* Chronologue
|
|
|
|
|
|
| Goal | Description | Priority | Status | |
|
|
|
| Build mock chronologue tool |We'll build the mock tool once we have the high-fidelity prototype. Probably after the Portland conference. | | |
|
|
|
| Design high-fidelity prototype | UX Team tests and iterates constantly. Prototype should be finished before Portland| High - In progress | |
|
|
|
| Create MVP version of API | Ian did most of the work for this task. We have an API that works, but we still need to figure out where to host it, so it's accessible on the web. | High - Finished | |
|
|
|
| Goal | Description | Priority | Status |
|
|
|
| Create MVP version of API | Ian did most of the work for this task. We have an API that works, but we still need to figure out where to host it, so it's accessible on the web. | High | Finished |
|
|
|
| Design high-fidelity prototype | UX Team tests and iterates constantly. Prototype should be finished before Portland| High | In progress |
|
|
|
| Build mock chronologue tool | We'll build the mock tool once we have the high-fidelity prototype. Probably after the Portland conference. | | |
|
|
|
| *Stretch Goals* | | | |
|
|
|
| Identify documentation needs and IA | Including whether templates exist for them | | |
|
|
|
| Research potential doc tools setup | We will probably use a Hugo & Docsy setup to test drive the doctools' group material. In the meantime, we will start drafting documentation using Markdown based on the templates that are ready for QA. | | |
|
|
|
|
... | ... | |