[BB-5510/SE-5376] SprintCraft not allocating time for assignment to other cell's tickets
Story
"As a cell member, I want SprintCraft to allocate time for all my commitments so that I can plan my sprint."
Full description
During Sprints 264 - 266, Jill was assigned to task SE-5256. However, SprintCraft didn't recognize this as one of her tasks, and so didn't allocate time for it in the Falcon Sprint planning report.
Maybe it's because it's an SE task, but Jill is in Falcon?
Completion criteria
- Task assignments in a project outside of someone's cell appear as commitments just like task assignments inside someone's cell.
- Automated testing must cover common paths in behavioral specification.
Documentation updates & improvements criteria
- If some specific task settings are required to achieve this, please document them in the SprintCraft user docs.
Edited by Boros Gábor