We need a plan that we can execute constantly on the current infrastructure as well as on new realeases as they are deployed to test, staging and production. In general, we should aim towards all of the tests being automated to expedite testing and give us a report for each release / current status performance. We will also have to complete some manual tests that test the latest functionality we have delivered in a release.

Why is this feature important?

We need to expedite testing to understand any breaking changes or performance issues we introduce through code changes.

Work Breakdown Structure (WBS)

Task Description Duration Status Start Date End Date Comment
1 Identify and write-down the installation test case in end user's perspective 1D Done 06 Oct 23 09 Oct 23
2 Identify and write-down the device onboarding test cases in end user's perspective 1D Done 10 Oct 23 10 Oct 23
3 Migrate the test cases for task #1 (closed) and #2 (closed) in Test link setup locally. 1D Done 31 Oct 23 31 Oct 23
4 Identify and write-down the ML job scheduling test cases on SPD application in end user's perspective 1D Done 01 Nov 23 01 Nov 23
5 Troubleshoot the setup so that I can refer the system behavior to design the test cases 1D Done 02 Nov 23 03 Nov 23 Issue with oracle and may be with other component due to which I was unable to run job on SPD. Tried with latest and dev versions of build but the same observation. Posted the observation on Dev channel as well.
6 Identify and write-down claiming a job test cases on CPD in end user's perspective 1D Done 03 Nov 23 03 Nov 23