Implement firecracker executor
Estimation
Story points: 4 SP
Estimated focus duration (perfect conditions): 4 days
Estimated pessimistic duration (worst case scenario): 6 days
Description
Click to expand
Who
What
- Implement firecracker executor sub-package following the new interface designed in #346.
How
Why
When
Acceptance Criteria
Click to expand
Work Breakdown Structure (WBS)
Task | Description | Duration | Status | Start Date | End Date | Comment |
---|---|---|---|---|---|---|
A | Design firecracker executor | 1 Day | Done | Apr 1 | Apr 3 | |
B | Implement firecracker handler interface | 1 Day | Done | Apr 3 | Apr 5 | |
B | Implement firecracker executor | 1 Day | Done | Apr 3 | Apr 5 |
Edited by Dawit Abate