Background tasks scheduler
Estimation
Story points : 5 SP
Estimated focus duration: 5 days
Estimated pessimistic duration: 8 days
Description
Who
- @dawit.abate
- @dagiopia - advisor, reviewer
What
Design and implement a background task scheduler to manage routines that are run by the DMS internally.
How
Why
Currently multiple tasks are run in the DMS in different packages and have no central scheduler to manage tasks. This leads to unpredictable resource usage and makes it hard to manage tasks.
Acceptance Criteria
Click to expand
Work Breakdown Structure (WBS)
Task | Description | Duration | Status | Start Date | End Date | Comment |
---|---|---|---|---|---|---|
A | Research on existing approaches | 5Hr | Done | Nov 30 | Dec 1 | |
B | Design the scheduler | 2 Days | Done | Dec 1 | Dec 4 | |
C | Implementation | 5 Days | Done | Dec 5 | Dec 11 | |
D | Tests | 1 Day | Done | Dec 11 | Dec 12 |
Edited by Dawit Abate