specification for executor package
SP: 5
Estimated focus duration (perfect conditions): 5 days
Estimated pessimistic duration (worst case scenario): 7 days
Who
- @0xPravar @dawit.abate
- @kabir.kbr -- advisor
What
- Write specification for
executor
package implementation
How
Why
When
- Refer to project management portal
Acceptance Criteria
Click to expand
- Specification should accurately reflect the code
- All Data models created
- All sequence diagrams created
- All gherkin feature files created
- Alignment with other design of other packages
Work Breakdown Structure (WBS)
Task | Description | Duration | Status | Start Date | End Date | Comment |
---|---|---|---|---|---|---|
A | Specification for general Executor functionality | 2 Days | Done | 15-April | 16-April | |
B | Specification for docker implementation | 2 Days | Done | 18-April | 19-April | Reference MR |
C | Specification for firecracker implementation | 3 Days | Done | 22-April | 24-April | Reference MR |