Support for Cardano Node Deployment
Milestone Deliverables
No | Deliverable | Timeline | Proof |
---|---|---|---|
1 | Estimated the status of the project and technical challenges remaining, considering platform developments in the meantime, for implementing it as provided in the original proposal funded via Catalyst Fund 7 | To be done by Feb 1, 2024 | Technical deliverables and project plan |
2 | Enables SPOs to run computing workflows on community provisioned hardware, increasing resilience and aiding decentralisation -- according to the revised plan. | To be done by March 31, 2024 | Tested via community SPOs and partners |
Context
- Original milestone (expired): https://gitlab.com/groups/nunet/-/milestones/19
- Project's short summary;
- Full proposal on Catalyst
- Full proposal on GDrive.
- @dagimsisay 's presentation with the first estimation of the work needed for continuation of the project: link;
- Proposed project scope definition based on which the milestone is planned: link;
Edited by kabir