All issues for this milestone are closed. You may close the milestone now.
Expired
Milestone Apr 21, 2025–Jun 15, 2025

FM Readines [Subsystem Level]

  • All FM COTS tested
  • All FM in-house delivered and tested
  • Internal Test Sensors integrated
  • All harness ready (internal & TVAC)
  • Work Stations in Clean Room are ready
  • All documentation ready (assembly guide, test process, launch readiness etc.)
  • Work items 51
  • Merge requests 3
  • Participants 8
  • Labels 5
Loading
Loading
Loading
Loading
100% complete
100%
Start date
Apr 21, 2025
Apr 21
-
Jun 15 2025
Due date
Jun 15, 2025 (Past due)
51
Work items 51
Open: 0 Closed: 51
None
Total weight
None
3
Merge requests 3
Open: 0 Closed: 0 Merged: 3
1
Release
Assemply v0.1.2
Reference: librespacefoundation/phasma%"FM Readines [Subsystem Level]"