Milestone Jan 3, 2022–Jan 21, 2022

Sprint 2022-1

Conversion Crew

SPRINT GOALS:

  1. Tech debt issues (table plugin, card component, network/sentry errors, etc ... )

  2. Adjustments of various UX components (table headers, input component, global UX padding, etc... )

  3. Refactoring of the sidebar into the SPA context

  4. Portfolio bugs fixes

STATUS:

  • planned: 28 tickets (47 story points)
  • covered: 26 tickets (39 story points) + 12 bugs
Week # Total Done Doing To do # Bugs
Week 1-3 47 39 8 0 12
  • Work items 0
  • Merge requests 0
  • Participants 0
  • Labels 0
Loading
Loading
Loading
Loading
100% complete
100%
Start date
Jan 3, 2022
Jan 3
-
Jan 21 2022
Due date
Jan 21, 2022 (Past due)
0
Work items 0
Open: 0 Closed: 0
None
Total weight
None
26
Merge requests 26
Open: 0 Closed: 0 Merged: 26
0
Releases
None
Reference: capinside%"Sprint 2022-1"