Expired
Milestone
Sep 20, 2021–Oct 8, 2021
Sprint 2021-13
Activation Crew
Sprint goals:
- Member facing solutions of tagging are releasable to new members
- Small newsletter improvements
- Integrate auto-guide to review app
- Dev capacity at planning: 42 -> 50%: 21
Status:
- planned: 17 tickets (26 story points)
- 10 story points were inherited from the last sprint
| Week # | Total | Done | Doing | To do | # Bugs |
|---|---|---|---|---|---|
| Week 1 | 26 | ||||
| Week 2 | |||||
| Week 3 |
Conversion Crew
SPRINT GOALS:
- Portfolio frontend (90% done)
- Portfolio backend + tracking (90% done)
- Full-screen modal for performance charts (done)
- Front-end components consistency (WIP)
STATUS:
- planned: 23 tickets (53 story points)
- covered: 18 tickets (46 story points) + 12 bugs
| Week # | Total | Done | Doing | To do | # Bugs |
|---|---|---|---|---|---|
| Week 1 | 53 | 20 | 23 | 10 | 5 |
| Week 2 | 57 | 27 | 26 | 5 | 9 |
| Week 3 | 59 | 46 | 13 | 0 | 12 |