Closed
Milestone Aug 30, 2021–Sep 17, 2021

Sprint 2021-12

Conversion Crew

SPRINT GOALS:

  1. Portfolio frontend (80% done)
  2. Portfolio backend + tracking (95% done)
  3. Website performance improvements / frontend consistency (async frontend deployed)
  • Homepage mobile: 18 -> 20

  • Homepage desktop: 32 -> 66

  • Articles mobile: 20 -> 22

  • Articles desktop: 49 -> 73

STATUS:

  • planned: 24 tickets (48 story points)
  • 25 story points were inherited from the last sprint
Week # Total Done Doing To do # Bugs
Week 1 48 6 10 29 3
Week 2 54 16 30 8 6
Week 3 63 47 16 0 7

Activation Crew

SPRINT GOALS:

  1. Newscenter tracking (done)
  2. Interest selection for a returning member (90%)
  3. Interest selection for a new member (70%)
  • Total dev capacity on the planning: 41 -> 50% ~21

STATUS:

  • planned: 14 tickets (26 story points)
  • 5 story points were inherited from the last sprint
Week # Total Done Doing To do # Bugs
Week 1 26
Week 2 26 2
Week 3 26 16 10
  • Work items 0
  • Merge requests 0
  • Participants 0
  • Labels 0
Loading
Loading
Loading
Loading
100% complete
100%
Start date
Aug 30, 2021
Aug 30
-
Sep 17 2021
Due date
Sep 17, 2021 (Past due)
0
Work items 0
Open: 0 Closed: 0
None
Total weight
None
64
Merge requests 64
Open: 0 Closed: 0 Merged: 64
0
Releases
None
Reference: capinside%"Sprint 2021-12"