Closed
Milestone
Aug 30, 2021–Sep 17, 2021
Sprint 2021-12
Conversion Crew
SPRINT GOALS:
- Portfolio frontend (80% done)
- Portfolio backend + tracking (95% done)
- Website performance improvements / frontend consistency (async frontend deployed)
-
Homepage mobile: 18 -> 20
-
Homepage desktop: 32 -> 66
-
Articles mobile: 20 -> 22
-
Articles desktop: 49 -> 73
STATUS:
- planned: 24 tickets (48 story points)
- 25 story points were inherited from the last sprint
| Week # | Total | Done | Doing | To do | # Bugs |
|---|---|---|---|---|---|
| Week 1 | 48 | 6 | 10 | 29 | 3 |
| Week 2 | 54 | 16 | 30 | 8 | 6 |
| Week 3 | 63 | 47 | 16 | 0 | 7 |
Activation Crew
SPRINT GOALS:
- Newscenter tracking (done)
- Interest selection for a returning member (90%)
- Interest selection for a new member (70%)
- Total dev capacity on the planning: 41 -> 50% ~21
STATUS:
- planned: 14 tickets (26 story points)
- 5 story points were inherited from the last sprint
| Week # | Total | Done | Doing | To do | # Bugs |
|---|---|---|---|---|---|
| Week 1 | 26 | ||||
| Week 2 | 26 | 2 | |||
| Week 3 | 26 | 16 | 10 |