Closed
Milestone
Jul 19, 2021–Aug 6, 2021
Sprint 2021-10
Activation Crew
Sprint goals:
- new design of the interest tag selection in user settings (done)
- retention analysis (data analysis only, no development) (done)
Note: The dev team's availability is ~30% due to holidays. There was no sprint planning, just committing to the goals and the corresponding tickets.
Conversion Crew
Sprint goals:
- Watchlist (done)
- Alternative products - backend split (80% done)
- Portfolio (backend prep work done)
- Website performance improvements (70% done)
Status:
- planned: 25 tickets (34 story points)
- 11 story points were inherited from the last sprint
| Week # | Total | Done | Doing | To do | # Bugs |
|---|---|---|---|---|---|
| Week 1 | 34 | 7 | 19 | 8 | 1 |
| Week 2 | 47 | 24 | 15 | 8 | 8 |
| Week 3 | 56 | 41 | 15 | 0 | 11 |