Closed
Milestone
Jun 7, 2021–Jun 25, 2021
Sprint 2021-8
Power Squad
Sprint goal/s:
- Alternative products - backend split (70% done)
- Comparison Overview page (done)
- Comparison Tool (done)
- Watchlist (50% done)
Status:
- planned: 21 tickets (41 story points)
- 10 story points were inherited from the last sprint
| Week # | Total | Done | Doing | To do | # Bugs |
|---|---|---|---|---|---|
| Week 1 | 41 | 3 | 23 | 15 | 0 |
| Week 2 | 46 | 11 | 28 | 7 | 1 |
| Week 3 | 48 | 38 | 4 | 6 | 3 |
Social Squad
Sprint goals:
- 1:N messaging (done)
- Event tiles (80% done)
- Newsletter optimization, marketing campaign support (continuous fastlane)
Status:
- planned: 13 tickets (25 story points)
- 5 story points were inherited from the last sprint
- 1 story (event tile in messaging) pulled out for the sake of the lunchbreak restructuring
- with Kash as extra man power, we also delivered for the interest tagging to articles, live within a couple of days
| Week # | Total | Done | Doing | To do | # Bugs |
|---|---|---|---|---|---|
| Week 1 | 26 | 6 | 10 | 10 | 2 |
| Week 2 | 27 | 9 | 11 | 7 | 2 |
| Week 3 | 30 | 19 | 11 | 0 | 4 |