Milestone Jun 7, 2021–Jun 25, 2021

Sprint 2021-8

Power Squad

Sprint goal/s:

  1. Alternative products - backend split (70% done)
  2. Comparison Overview page (done)
  3. Comparison Tool (done)
  4. Watchlist (50% done)

Status:

  • planned: 21 tickets (41 story points)
  • 10 story points were inherited from the last sprint
Week # Total Done Doing To do # Bugs
Week 1 41 3 23 15 0
Week 2 46 11 28 7 1
Week 3 48 38 4 6 3

Social Squad

Sprint goals:

  1. 1:N messaging (done)
  2. Event tiles (80% done)
  3. Newsletter optimization, marketing campaign support (continuous fastlane)

Status:

  • planned: 13 tickets (25 story points)
  • 5 story points were inherited from the last sprint
  • 1 story (event tile in messaging) pulled out for the sake of the lunchbreak restructuring
  • with Kash as extra man power, we also delivered for the interest tagging to articles, live within a couple of days
Week # Total Done Doing To do # Bugs
Week 1 26 6 10 10 2
Week 2 27 9 11 7 2
Week 3 30 19 11 0 4
  • Work items 0
  • Merge requests 0
  • Participants 0
  • Labels 0
Loading
Loading
Loading
Loading
100% complete
100%
Start date
Jun 7, 2021
Jun 7
-
Jun 25 2021
Due date
Jun 25, 2021 (Past due)
0
Work items 0
Open: 0 Closed: 0
None
Total weight
None
77
Merge requests 77
Open: 0 Closed: 4 Merged: 73
0
Releases
None
Reference: capinside%"Sprint 2021-8"