Closed
Milestone
Apr 6, 2021–Apr 25, 2021
Sprint 2021-5
Power Squad
Sprint goal/s:
- Product Details Page release (done)
- Article series component (done)
- New article layouts(testing)
- New article tiles (done)
- Gnews & Improved gating (testing)
Status:
- planned: 27 tickets (62 story points)
| Week # | Total | Done | Doing | To do | # Bugs |
|---|---|---|---|---|---|
| Week 1 | 62 | 26 | 18 | 18 | 0 |
| Week 2 | 65 | 30 | 22 | 13 | 2 |
| Week 3 | 68 | 48 | 20 | 0 | 0 |
Social Squad
Sprint goal/s:
- Der CAPinsider is deployed to members (done)
- V360 Inactive badge for for Honorary advisors (done)
- Pool members can reg as prof only (done)
Status
- originally planned: 38 story points aka man days (for 13 out of the 38 coding & testing done but not deployed)
- got extra resource on Week 2 (Sven)
- already started working on future goals
| Week # | Total | Done | Doing | To do | # Bugs |
|---|---|---|---|---|---|
| Week 1 | 38 | 18 | 8 | 12 | 1 |
| Week 2 | 43 | 30 | 10 | 3 | 2 |
| Week 3 | 43 | 37 | 6 | 0 | 1 |