Closed
Milestone Jan 1, 2021–Feb 21, 2021

Scaffold Grey Software V3

The first Grey software was built by myself, a number of paid students, and volunteers. It started in May 2020 and ended in August 2020. During this time, the organization was focused on teaching a handful of students to build out our portfolio of apps which included Toonin, Material Math, and the Focus extensions.

The second Grey Software was an organization that was formally registered in Canada, but the students that were working with me in the summer had to move back to school or on to bigger things. At this time, I moved back to Pakistan and tried to climb the pioneer tournament ranks. The structural problems present as a result of a lone wolf mentality from the first Grey software were still present, but I learned and discovered new technologies, and built important open-source relationships.

The third Grey software is an attempt to restructure the organization into a functioning organism that

  • Effectively moves financial capital towards open source creators and teachers
  • Sets up a technologically empowering environment for creative humans to maximize their contributing potential
  • Delivers useful products for humans
  • Runs successful for-credit programs with universities

This vision will take some time to properly set up and execute, but by setting a target for February 22nd, which is when we start our edu program with UET Mardan. We'll try to manifest as much of this vision for that batch of students so that we can have a fantastic pilot program.

  • Work items 5
  • Merge requests 0
  • Participants 4
  • Labels 1
Loading
Loading
Loading
Loading
100% complete
100%
Start date
Jan 1, 2021
Jan 1
-
Feb 21 2021
Due date
Feb 21, 2021 (Past due)
5
Work items 5 New issue
Open: 0 Closed: 5
0
Merge requests 0
Open: 0 Closed: 0 Merged: 0
0
Releases
None
Reference: grey-software/org%"Scaffold Grey Software V3"