Shut down GCP Cluster: gl-remote-dev-stg-0c1d2143
Overview
The legacy cluster gl-remote-dev-stg-0c1d2143 is planned to be shut down by 20th of December due to cost and operational maintenance burdens.
This's a long overdue cleanup since the dissolution of engineering productivity team.
This cluster has been configured for internal use only.
Impacted users and groups
Per usage, there're 40 GitLab team members who are running their workspaces on this cluster, 34 active workspaces in 10 months as the highest record.
Alternative solutions
GitLab team members are advised to pursue the alternatives suggested here by Runners Core group (e.g. previously remote development group).
For additional support about workspaces, GitLab team members should reach out to Runners Core group.
Shutdown Strategy & Timeline
Phase 1: Assessment & Communication (Weeks 1-2)
DRI: Development Tooling
-
Usage Analysis: analyse cluster usage and curate impact -
Stakeholder Alignment: Coordinate with Runners Core group on messaging and alternatives -
Communication Launch: Post initial announcement on engineering-fyi with clear timeline
Phase 2: Migration Support (Weeks 3-8)
DRI: Core Runners
-
Alternative Setup: Provide hands-on migration assistance to high-usage team members -
Documentation: Create step-by-step migration guides for each alternative solution -
Office Hours: Host weekly "migration office hours" for troubleshooting -
Progress Tracking: Monitor migration progress and identify stragglers
Phase 3: Graceful Shutdown (Weeks 9-12)
DRI: Development Tooling
-
Final Warnings: Send escalating reminders (4 weeks, 2 weeks, 1 week before shutdown) -
Data Backup: Ensure any critical workspace data is preserved -
Controlled Shutdown: Gradually reduce cluster capacity to encourage migration -
Final Cutoff: Complete shutdown by December 20, 2025
Timeline
| Week | Date Range | Activities | Milestone | DRI |
|---|---|---|---|---|
| 1-2 | Oct 28 - Nov 8 | Usage analysis, stakeholder alignment, initial communication | Communication launched | Developer Tooling |
| 3-4 | Nov 11 - Nov 22 | Migration guides, office hours setup, individual outreach | Support infrastructure ready | Core Runners |
| 5-6 | Nov 25 - Dec 6 | Active migration support, progress tracking | 50% users migrated | Core Runners |
| 7-8 | Dec 9 - Dec 20 | Final warnings, data backup, controlled shutdown | 100% migration complete | Developer Tooling |
Success Metrics
- Migration Rate: Target 90% user migration by Week 6
- Support Tickets: Minimize post-shutdown support requests
- Cost Savings: Achieve planned operational cost reduction
- User Satisfaction: Maintain productivity during transition
Communication
-
Prepare a message and post it on engineering-fyi after aligning with Runners Core group (e.g. previously remote development group). -
Send reminders every month and 2 weeks before the deadline. -
Use multiple channels: Slack notifications, email updates, dedicated support channel -
Executive sponsorship message for resistant users
Edited by Mohga Gamea