Product Intelligence 14.7 Milestone Planning
14.7 Reference Information
- 14.7 Milestone period: 2021-12-23 - 2022-01-17
- Breakdown Phase 2021-12-18 - 2021-12-22: break down work, weigh issues, FE/BE collaboration
- 14.6 Retro https://gitlab.com/gl-retrospectives/product-intelligence/-/issues/22
- 14.5 Retro https://gitlab.com/gl-retrospectives/product-intelligence/-/issues/21
- Holiday time: Please add the amount of time off taken for the release period in the Capacity Planning Spreadsheet
Issue Boards
- Product Intelligence Issue Board -by milestone
- Product Intelligence Issue Board -by workflow label
- PM Issue Board
Some notes about the board by milestone-
- The issue board by milestone contains the current milestone as well as a list for the next two milestones. Not only will this help me plan easier, but it will give the dev team visibility into the next priorities.
- Issues within each milestone list are prioritized with the highest priority issues ranked from top to bottom, please pick issues in order wherever possible.
- If there is nothing left to pick in the current milestone, there is a list of options to follow in picking something to work on
- We aim to plan ambitiously. This means it is ok if we don't get through all planned issues in a single milestone. However, issues marked with Deliverable are issues we are committing to deliver in the current milestone. These are the highest priority.
14.7 Summary
Coming into milestone 14.7, we are carrying over open work from 14.6 and are committing to progress in the following areas:
- Data insights
- Null user ID pseudonymization
- Issues resulting from the spike on Connecting Snowplow hashed user IDs with Snowflake Database
- Reliability
- Instrumentation classes
Milestone breakdown
Type | # of Issues | Total Weight | % of Total Weight | Target % |
---|---|---|---|---|
Deliverable | 3 | 11 | 11.70% | 30% |
System Reliability and Monitoring | 4+ | 18 | 19.15% | 25% |
Tech Debt | 2 | 8 | 8.51% | 10% |
Bugs | 3 | 11 | 11.7% | 10% |
Tooling | 1 | 4 | 4.26% | n/a |
Documentation | 5 | 9 | 9.57% | n/a |
Technical Spike | 5 | 25 | 26.6% | n/a |
Weight by Workflow Label at beginning of milestone
🚨 Issues scheduled for 14.7 which need weight
Other | Ready for Dev | In Dev | Ready for Review | In Review | Staging | Verification/Closed | Blocked | Total |
---|---|---|---|---|---|---|---|---|
7 | 42 | 27 | - | 7 | - | - | 1 | 84+ |
- + denotes unweighted issues in milestone
- "Other" = all workflow labels prior to workflowready for development
Milestone Weight History
BACKEND | 14.0 | 14.1 | 14.2 | 14.3 | 14.4 | 14.5 | 14.6 |
Total assigned | 53 | 58 | 67 | 55 | 74 | 95 | 84 |
Deliverable | 8 | 3 | 13 | 18 | 9 | 5 | 9 |
Unplanned | 15 | 13 | 4 | 24 | 11 | 5 | 3 |
Pushed to next milestone | 9 | 19 | 31 | 20 | 26 | 36 | 42 |
Closed | 59 | 52 | 40 | 59 | 59 | 64 | 45 |
FRONTEND | 14.0 | 14.1 | 14.2 | 14.3 | 14.4 | 14.5 | 14.6 |
Total assigned | 16 | 15 | 21 | 9 | 18 | 11 | 10 |
Deliverable | 2 | 0 | 0 | 6 | 11 | 4 | 1 |
Unplanned | 1 | 4 | 7 | 10 | 0 | 0 | 4 |
Pushed to next milestone | 3 | 4 | 10 | 2 | 8 | 4 | 4 |
Closed | 14 | 15 | 18 | 17 | 10 | 7 | 10 |
*denotes pending issues from prior milestone which may push or close
Edited by Amanda Rueda