Wrong "Open issues" number on Burndown chart
Summary
Wrong "Open issues" number on Burndown chart
Steps to reproduce
See https://gitlab.com/groups/gitlab-org/-/milestones/15
What is the expected correct behavior?
The two numbers should be the same
Relevant logs and/or screenshots
Output of checks
This bug happens on GitLab.com
Findings
The X-axis of the graph is based on the milestone's start and due date. So we only show the counts here for those dates. While the number on the sidebar are the current counts.
These could be inconsistent if there are changes to the count after the due date. For example:
- An issue is created after the milestone due date and assigned that milestone.
- An issue is closed after the due date.
- The milestone due date is moved earlier resulting to issues being opened / closed after the due date.
Edited by 🤖 GitLab Bot 🤖