Current status

During the UX scorecard work, I realized there were several different statuses that Geo sub-pages have. I wasn't sure at the beginning, the statuses were intentionally designed in this way. So I created this issue and need our team's valuable inputs.

/projects page

Tab Status
Synced In sync
Pending Pending synchronization
Pending Pending verification
Failed Failed
Never Never

/uploads page

Tab Status
Synced In sync
Failed Failed
Never Never

/designs page

Tab Status
Synced Synced
Pending Pending synchronization
Failed Failed

Questions

  • Do we need never? If yes, do we also need it for the designs?
  • Do we need pending only for the projects?

Examples

  • For example, we are using different icons of synced status on the /designs page with different naming.
Design page Others
Screenshot_2020-02-11_at_11.09.34 Screenshot_2020-02-11_at_11.10.15
  • The style of the icons look different visually. The failed status is only using the filled-type icon, not the line-type. Screenshot_2020-02-11_at_11.08.12

Proposal

  • Having two different states: synchronization and verification.
  • Each state could include several different statuses.

image

Next steps

  • As @fzimmer mentioned #204837 (comment 440771402) open a discussion for the terminology (replication & synchronization)
  • Breaking it into several issues for implementation 🔮

Intended users

System administrators

Relevant link