Track delays in roadmap view
- Create epic as high-level idea
- Use top-level planning with fixed dates and view in roadmap
- Break down into individual issues
- Weight issues
- Assign issues to individual milestones, using a board, and observing available capacity per milestone
- Use inherited dates, but also keep fixed dates, where fixed dates represent initial contracts/target dates
- View both fixed dates and inherited dates on roadmap, so you can see delays