Group Gantt view of group milestones and epics
Problem
- View status of proposed/future work, ongoing work, and completed work at a portfolio level. This means visualizing work status across multiple teams and departments.
- These are "rolled-up" views in many different tools.
- This allows for resource planning over time. (But is out of scope for this issue. We just focus on the view for now.)
- This allows for "what if scenarios". E.g. if I take resources from one project (or group of projects), and allocate them to another, how does that affect the estimated timelines in each?
Description
- Each group has a Gantt view of all group milestones and epics of that group.
- Show all milestones as a horizontal bar, indicating start and due dates. Show that some milestones ended early and some were late.
- Show milestones that are behind schedule / ahead of schedule, will be late / will be early.
- Need to have a new field for the milestone object,
velocity
. This is a user-entered value to estimate how quickly the team is working.
- Need to have a new field for the milestone object,
- Show epics along the time scale as well. The time bar for an epic comes from the earliest start date of all milestones across all the issues in that epic, and the latest due date or latest date an issue was closed.
- Need additional work to specify edge cases, what happens when start dates, due dates, velocity fields are not specified.
Edited by Victor Wu