13.11 Fulfillment:Purchase Planning Issue
13.11 Milestone Information
-
Purchase 13.11 board
- This board is segmented by lists by team label
- Issues within each list are prioritized with the highest priority issues ranked from top to bottom, please pick issues in order wherever possible
- Issues marked with Deliverable are issues we are committing to deliver in the current milestone
- 13.11 Milestone period: 2021-03-18 - 2021-04-17
- Kick-off planning recording: coming soon
13.11 Summary
💪🏽 Priority Projects
These are projects which span multiple milestones and have high visibility internally and/or require customer communication and therefore a hard target delivery date.
Project | Parent | Target Delivery |
---|---|---|
Quarterly Self-Managed Seat Reconciliation & Billing | Super Sonics | 14.1 |
Quarterly GitLab.com Seat Reconciliation & Billing | Super Sonics | 14.1 |
🍦 Deliverables
These are issues we are committing to deliver in the current milestone and should be prioritized above non-priority, non-deliverables.
🚧 Tech Debt
- [CI Minutes] Re-expose CI plan minutes data through GraphQL in GL.com
- Add feature specs for Upgrade Offer scenarios
Weight by Workflow Label at beginning of milestone
Team | Ready for Dev | In Dev | In Review | Staging | Verification | Total |
---|---|---|---|---|---|---|
Frontend | 3 | 15 | - | - | - | 29 |
Backend | 13 | 20 | 16 | - | - | 49 |
+ denotes unweighted issues in milestone
🌴 Holiday Time
Please add your holiday dates below for the 13.11 release period and don't forget to add to the Fulfillment calendar.
Holiday Time | |
---|---|
PM | |
Tatyana | |
Frontend | |
Ragnar | |
Ammar | |
Vitaly | |
Andrei | |
Angelo | |
Michael |
|
Backend | |
Chris | 6 April |
Shreyas |
|
Ryan | |
Reuben | |
Qingyu |
|
Josianne |
|
UX | |
Emily |
|
Quality | |
Chloe | Quality oncall 03/29 - 04/02 |
Dan |
Milestone Weight History
FRONTEND | 13.3 | 13.4 | 13.5 | 13.6 | 13.7 | 13.8 | 13.9 |
Total assigned | 39 | 43 | 48 | 32 | 64 | 49 | 55 |
Deliverable | 14 | 18 | 10 | 7 | 6 | 3 | 2 |
Unplanned | 5 | 26 | 17 | 52 | 38 | 32 | 37 |
Pushed to next milestone | 20 | 14 | 26 | 42 | 42 | 32 | 20 |
Closed | 24 | 55 | 39 | 42 | 60 | 49 | 72 |
BACKEND | 13.3 | 13.4 | 13.5 | 13.6 | 13.7 | 13.8 | 13.9 |
Total assigned | 22 | 30 | 38 | 27 | 43 | 40 | 47 |
Deliverable | n/a | n/a | n/a | n/a | 5 | 11 | 6 |
Unplanned | 3 | 0 | 7 | 11 | 7 | 19 | 4 |
Pushed to next milestone | 17 | 18 | 7 | 18 | 28 | 35 | 16 |
Closed | 8 | 12 | 24 | 20 | 22 | 24 | 35 |
Edited by Tatyana Golubeva