Source Code Group 14.9 Planning (March 22)

Release planning for the Source Code Group

Overview

Event Date
Release Start Date 2/18/2022
Feature Freeze 3/17/2022
Release Date 3/22/2022
Milestone Workdays 20

Build Boards

Goals

  1. Exit Engineering Allocation - complete any remaining work
  2. FIPS compliance - We want to prioritize getting this done because it is a requirement for FEDRAMP which is a significant opportunity for GitLab as a whole. &6476 (closed)
  3. P2 bugs - We've got lots and need to work on triaging and prioritizing the big ones.

Team Capacity

  • Total Weight Capacity: TODO
  • FE Weight: TODO
  • BE Weight: 23

Planning - Planning Board

Product manager prepares the planning with proposed issues for the milestone. Engineering reviews and make recommendations based engineering allocation and capacity.

Checklist

Engineering Managers

  • Get Team Capacities and post them in a comment no later than the 10th of the month
    • Backend
    • Frontend
  • Obtain weights for proposed issues
  • Recommend issues via engineering allocation as applicable
  • Assign ~Direction Items for Milestone

Product Manager

  • Define Key Themes
  • Prepare planning board and submit it for initial capacity assessment and review
  • Signs off on final plan
Edited by Sarah Waldner