Source Code Group 14.9 Planning (March 22)
Release planning for the Source Code Group
Overview
| Event | Date |
|---|---|
| Release Start Date | 2/18/2022 |
| Feature Freeze | 3/17/2022 |
| Release Date | 3/22/2022 |
| Milestone Workdays | 20 |
Build Boards
Goals
- Exit Engineering Allocation - complete any remaining work
- FIPS compliance - We want to prioritize getting this done because it is a requirement for FEDRAMP which is a significant opportunity for GitLab as a whole. &6476 (closed)
- P2 bugs - We've got lots and need to work on triaging and prioritizing the big ones.
Team Capacity
- Total Weight Capacity: TODO
- FE Weight: TODO
- BE Weight: 23
Planning - Planning Board
Product manager prepares the planning with proposed issues for the milestone. Engineering reviews and make recommendations based engineering allocation and capacity.
Checklist
Engineering Managers
-
Get Team Capacities and post them in a comment no later than the 10th of the month -
Backend -
Frontend
-
-
Obtain weights for proposed issues -
Recommend issues via engineering allocation as applicable -
Assign ~Direction Items for Milestone
Product Manager
-
Define Key Themes -
Prepare planning board and submit it for initial capacity assessment and review -
Signs off on final plan
Edited by Sarah Waldner