Sec. SSCS [Co-Create Initiatives]

Please follow instructions here (&2554). If needed, please assign team PMs to assist in further defining co-create initiatives for your stage.

Please evaluate with your applicable engineering manage based on the following criteria:

Scope and complexity of the initiative

  • Technical requirements and complexity
  • Anticipated lead time to engage and capacity plan

Label as:

  • Small (2-4 weeks)
  • Medium (1-2 months)
  • Large (quarter or more)

Resource requirements

  • Engineer level needed for specific effort (i.e. Junior, Staff, etc.)
  • Design and UX resources
  • Testing and quality assurance needs
  • Documentation requirements

Label as:

  • General (Junior, Intermediate, etc.)
  • Specialized (Specific skill set needed for developer)
  • Expert (Principal / Staff engineer needed)

Lead time

  • Expectations on the amount of lead time our internal teams would need to make this initiative successful

Label as:

  • Weeks
  • Month
  • Quarter
  • Multi-Quarter
Product Area Scope and Complexity Resource Requirements Lead Time Issue
grouppipeline security Large (in-progress) Sent Developer on site already N/A Support AWS secrets manager as alternative to V... (gitlab-org/gitlab#29047 - closed)
groupauthentication Very Small (Not started) General (Intermediate engineer) < 1 week Add Configuration Option for Mandatory public e... (gitlab-org/gitlab#9828)
grouppipeline security Job artifacts should be encryptable (gitlab-org/gitlab#363548)
groupauthentication Not ready for Co-create https://gitlab.com/gitlab-org/gitlab/-/issues/353065+