2024-06-04: Duo Features Enabled setting cascades to subgroups and subprojects
Production Change
Change Summary
We are making updates to the duo_features_enabled setting so that when a parent group changes the value of the attribute, all children get the new value.
Relevant MRs:
Change Details
- Services Impacted - Gitlab.org, self-managed
-
Change Technician -
@jfypk - Change Reviewer - @alejandro
- Time tracking - unknown
- Downtime Component - none
Set Maintenance Mode in GitLab
If your change involves scheduled maintenance, add a step to set and unset maintenance mode per our runbooks. This will make sure SLA calculations adjust for the maintenance period.
Detailed steps for the change
Change Steps - steps to take to execute the change
Estimated Time to Complete (mins) - Estimated Time to Complete in Minutes
-
Set label changein-progress /label ~change::in-progress -
Turn cascade_duo_features_enabledflag on in for gitlab -
Test that changes are not impacting graphs/logs -
Turn on flag globally -
Test that changes are stable -
Remove feature flag -
Set label changecomplete /label ~change::complete
Rollback
Rollback steps - steps to be taken in the event of a need to rollback this change
Estimated Time to Complete (mins) - Estimated Time to Complete in Minutes
-
Turn off feature flag -
Revert gitlab-org/gitlab!145876 (merged) -
Set label changeaborted /label ~change::aborted
Monitoring
Key metrics to observe
- Metric: 5xx responses
- Location: https://dashboards.gitlab.net/d/RZmbBr7mk/gitlab-triage?from=1717052400000&orgId=1&to=1717070399000&var-backend=All&var-env=gstg&var-stage=main&var-type=All
- What changes to this metric should prompt a rollback: High 5xx responses that do not stabilize.
Change Reviewer checklist
-
Check if the following applies: - The scheduled day and time of execution of the change is appropriate.
- The change plan is technically accurate.
- The change plan includes estimated timing values based on previous testing.
- The change plan includes a viable rollback plan.
- The specified metrics/monitoring dashboards provide sufficient visibility for the change.
-
Check if the following applies: - The complexity of the plan is appropriate for the corresponding risk of the change. (i.e. the plan contains clear details).
- The change plan includes success measures for all steps/milestones during the execution.
- The change adequately minimizes risk within the environment/service.
- The performance implications of executing the change are well-understood and documented.
- The specified metrics/monitoring dashboards provide sufficient visibility for the change.
- If not, is it possible (or necessary) to make changes to observability platforms for added visibility?
- The change has a primary and secondary SRE with knowledge of the details available during the change window.
- The change window has been agreed with Release Managers in advance of the change. If the change is planned for APAC hours, this issue has an agreed pre-change approval.
- The labels blocks deployments and/or blocks feature-flags are applied as necessary.
Change Technician checklist
-
Check if all items below are complete: - The change plan is technically accurate.
- This Change Issue is linked to the appropriate Issue and/or Epic
- Change has been tested in staging and results noted in a comment on this issue.
- A dry-run has been conducted and results noted in a comment on this issue.
- The change execution window respects the Production Change Lock periods.
- For C1 and C2 change issues, the change event is added to the GitLab Production calendar.
- For C1 and C2 change issues, the SRE on-call has been informed prior to change being rolled out. (In #production channel, mention
@sre-oncalland this issue and await their acknowledgement.) - For C1 and C2 change issues, the SRE on-call provided approval with the eoc_approved label on the issue.
- For C1 and C2 change issues, the Infrastructure Manager provided approval with the manager_approved label on the issue.
- Release managers have been informed prior to any C1, C2, or blocks deployments change being rolled out. (In #production channel, mention
@release-managersand this issue and await their acknowledgment.) - There are currently no active incidents that are severity1 or severity2
- If the change involves doing maintenance on a database host, an appropriate silence targeting the host(s) should be added for the duration of the change.
Edited by Jeff Park