2026-10-06: Soft Production Change Lock for GitLab Transcend India
Production Change Lock
CR for the Soft PCL - https://handbook.gitlab.com/handbook/engineering/infrastructure-platforms/change-management/#soft-pcl
This CR will prevent deployments during the PCL period.
For a full description of restrictions please see https://handbook.gitlab.com/handbook/engineering/infrastructure-platforms/change-management/#production-change-lock-pcl
Lock Summary
Soft PCL during the GitLab Transcend event on 2026-10-06 in Bengaluru, India. Current schedule as per the event webpage: 2026-10-06T11:30Z (5 pm IST) to 2026-10-06T16:00Z (9:30 pm IST)
The Soft PCL will be set from a few hours before the event begins to a few hours after the event ends. This provides us enough time to respond to any issues created by the last deployment to GitLab.com before the PCL. The goal of this PCL is to avoid deployments to GitLab.com and ensure that the system is stable.
We were talking about coordination on a different issue as well: https://gitlab.com/gitlab-com/gl-infra/delivery/-/work_items/22370+.
Details
- Lock type - Soft
- Lock DRI - @dawsmith
- Start Date - 2026-10-06 03:00 UTC
- End Date - 2026-10-06 20:00 UTC
Detailed steps for the change
Change Steps - steps to take to execute the change
Estimated Time to Complete (mins) - 900
- On 2026-10-06 at 03:00 UTC, Set label ~"change::in-progress"
/label ~change::in-progress - On 2026-10-06 at 20:00 UTC, Set label ~"change::complete"
/label ~change::complete
Rollback
Rollback steps - steps to be taken in the event of a need to rollback this change
Estimated Time to Complete (mins) - 5
- Set label ~"change::aborted"
/label ~change::aborted
Change Reviewer checklist
- Check if the following applies:
- The scheduled day and time of execution of the change is appropriate.
- The change plan is technically accurate.
- The change plan includes estimated timing values based on previous testing.
- The change plan includes a viable rollback plan.
- The specified metrics/monitoring dashboards provide sufficient visibility for the change.
- Check if the following applies:
- The complexity of the plan is appropriate for the corresponding risk of the change. (i.e. the plan contains clear details).
- The change plan includes success measures for all steps/milestones during the execution.
- The change adequately minimizes risk within the environment/service.
- The performance implications of executing the change are well-understood and documented.
- The specified metrics/monitoring dashboards provide sufficient visibility for the change.
- If not, is it possible (or necessary) to make changes to observability platforms for added visibility?
- The change has a primary and secondary SRE with knowledge of the details available during the change window.
- The change window has been agreed with Release Managers in advance of the change. If the change is planned for APAC hours, this issue has an agreed pre-change approval.
- The labels blocks deployments and/or blocks feature-flags are applied as necessary.
Change Technician checklist
- Check if all items below are complete:
- The change plan is technically accurate.
- This Change Issue is linked to the appropriate Issue and/or Epic
- Change has been tested in staging and results noted in a comment on this issue.
- A dry-run has been conducted and results noted in a comment on this issue.
- The change execution window respects the Production Change Lock periods.
- For C1 and C2 change issues, the change event is added to the GitLab Production calendar.
- For C1 and C2 change issues, the SRE on-call has been informed prior to change being rolled out. (In #production channel, mention
@sre-oncalland this issue and await their acknowledgement.) - For C1 and C2 change issues, the SRE on-call provided approval with the eoc_approved label on the issue.
- For C1 and C2 change issues, the Infrastructure Manager provided approval with the manager_approved label on the issue.
- Release managers have been informed prior to any C1, C2, or blocks deployments change being rolled out. (In #production channel, mention
@release-managersand this issue and await their acknowledgment.) - There are currently no active incidents that are severity1 or severity2
- If the change involves doing maintenance on a database host, an appropriate silence targeting the host(s) should be added for the duration of the change.