team::Ops OKR proposal issue - FY25 Q2
Context
We are few weeks away from FY25 Q2 and it is time to start planning for OKRs. Let's use this issue to suggest possible ideas and discuss the best combination of ideas and scope to set us up for Q2.
FY25 Q1 State
This is the first partial quarter as the ~"team::ops" team. We had a late start getting our OKRs prioritized, but made good progress on them:
- Eliminate 1 Chef dependency in Infra by moving infra to Kubernetes
- Define the architecture, cost and interaction points for “regional recovery bulkhead” infrastructure
FY25 Q2 - What's next?
Over the last few weeks teamOps has been scoping out work for two epics that we want to be our main focus:
As well as beginning to track work we have inherited as former members of the General Team:
Using the scope of these three epics, please share your ideas for OKRs for FY25 Q2.
Timeline
- Due date for idea submission is set to
2024-04-17
- Due date of this issue - Creation of first draft of OKRs on the
2024-04-18
- Formalize our final draft for the OKRs by
2024-04-22
- Consolidate OKRs with Department OKRs by
2024-04-25
Those dates are also present on the SaaS Platforms Leadership Calendar, consider adding it to your calendars
Edited by Kam Kyrala