Automatically calculate the next planned release date
With planned releases, bug/security releases will be scheduled based on the following requirements:
- The time between each planned release must fit well inside the Release SLO of 23 days.
- Each range of versions should at least have two planned releases.
- Versions released in December and January are the exception due to low capacity.
At the moment, the next dates are being manually planned (example).
The purpose of this issue is to add a method to the gitlab-releases gem to calculate the next planned release date based on the requirements.
To do
-
Include a method on the gitlab-releases
gem to calculate the next patch release date gitlab-org/ruby/gems/gitlab-releases!32 (merged) -
Bump the gitlab-releases
version gitlab-org/ruby/gems/gitlab-releases!33 (merged)
Edited by Mayra Cabrera