Milestone Oct 8, 2018–Nov 19, 2018

Code cleanup and light refactoring

There are a bunch of small issues that have been raised recently, from variables names to code structure. Let's get them all cleaned up over the next couple weeks.

RETROSPECTIVE:

dju:

  • I learned during this milestone that it makes sense to communicate the excpected scope of a piece of work (especially if it think it's rather small) and provide some simple input-output examples. This will help less experienced coders to correctly gauge how much work they should spent / how efficient a solution is possible.
  • We had to change the deadline for this milestone 2 times (in the future we should maybe make a note here anytime we do this), leaving our reasons.
  • The last time we postponed the MS, we managed to stick to our timeframes and managed not to add more issues to the scope, (previously not)
  • Work items 10
  • Merge requests 7
  • Participants 3
  • Labels 2
Loading
Loading
Loading
Loading
100% complete
100%
Start date
Oct 8, 2018
Oct 8
-
Nov 19 2018
Due date
Nov 19, 2018 (Past due)
10
Work items 10 New issue
Open: 0 Closed: 10
7
Merge requests 7
Open: 0 Closed: 1 Merged: 6