Milestone %1 Nov 1, 2016–Mar 21, 2017

Board @ desk - Single developer

Set up that allows a developer to test the CIP kernel on the Beaglebone Black (CIP selected hardware platform) connected locally to her development machine using kernelci tools.

the beta release is expected on Wednesday Feb 22nd

Progress

40 issues: 16 open and 24 closed 2 merge requests: 0 open and 1 merged 61% complete Past due Total weight: 102
Unstarted Issues (open and unassigned)
1
Completed Issues (closed)
24
Work in progress (open and unassigned)
0
Waiting for merge (open and assigned)
0